Project Schedule

The following schedule identifies major steps in the planning process. The schedule will be adjusted as necessary throughout the duration of the project.

 

May 2015Project Kick-off Meeting with City Staff
May-July 2015Existing Conditions Data Collection and Baseline Analyses
June 16, 2015Stakeholder Interviews and Planning Commission Work Study Session
July 8, 2015Community Workshop 1: Visioning, Opportunities & Constraints
September 23, 2015Downtown Advisory Commitee 1: Orientation
October 14, 2015Community Workshop 2: Preliminary Design Concept
October 28, 2015Downtown Advisory Committee Meeting 2: Preliminary Design Concept
November 3, 2015Joint City Council/Planning Commission Study Session: Preliminary Design Concept
Winter-Spring 2016Preparation of Administrative Review Draft Specific Plan
Summer 2016Preparation of Public Review Draft Specific Plan
October 4, 2016 Planning Commission Workshop and Downtown Advisory Committee Meeting 3: Public Review Draft Specific Plan
February-April 2017 Public Hearings and Adoption of Final Specific Plan